The Brace Overcrossing reopened ahead of schedule on Friday, February, 6 at 4 PM.
Lift process was completed on January 29, 2015.

Next phase started in September 2015:

  • Demo bridge barriers – COMPLETE
  • Replace sidewalk – COMPLETE
  • Concrete Barrier and metal beam guardrail on I-80 at the bridge columns – COMPLETE
  • Update concrete bridge barriers, bridge barrier fence and metal beam guardrail at the approaches to the bridge
  • Erosion control
  • Drainage, permanent striping and signage